Project: Extension to Docklands Light Railway
Location: Canning Town, East London
Value: c£145,000,000
Start Date on Site: Spring 2005
Contract Period: 36 months
Civil Engineering Works:

The principal elements of construction include a major concrete trough structure, with retaining walls, to carry the DLR track between KGV Station and the northern approach to the tunnels.   The project also includes a cut and cover section to the northern end of the bored tunnels.

In addition there are works to protect the few properties which may be at risk of settlement effects arising from tunnelling; main trunk sewer diversions under Woolwich New Road and Burrage Road and track and signalling installation.

General Information:

The new route would leave the planned London City Airport line east of King George V station in North Woolwich and descend into bored tunnel, passing under the River Thames and surfacing again west of Burrage Road, alongside the National Rail line platforms at Woolwich Arsenal station.

Tenders are now under evaluation, contract award is anticipated late 2004.

Project information from Emap Glenigan. For more information on their sales leads service click here.

For a discussion of possible construction job vacancies on this & other live construction projects please get in touch.

Contact Us

To search and apply for the latest civil engineering contracting jobs or quantity surveying jobs available, please follow one of the links below.

Search Jobs in Civil Engineering Contracting

Search Jobs in Quantity Surveying

Maxim do no necessarily claim to be sole or approved suppliers of staff to any particular construction company involved in the projects described.